Project details:

  • Widen the road to three lanes: one in each direction, plus a shared center left-turn lane
  • Build a 3.5-metre-wide multi-use path for walking and cycling (north side)
  • Add a 1.5-metre-wide concrete sidewalk (south side)
  • Replace ditches with curbs and storm sewers, where possible
  • Adjust grading and driveways (some work may be on private property)
  • Upgrade 1,000 metres of sanitary sewer
  • Install a new traffic light at Nipissing Road and Childs Drive

Traffic impacts:

  • Traffic along the entire length of Nipissing will be allowed in the westbound direction only
  • This will remain in place until the Fall of 2026

Work completed to-date (May 26, 2026):

  • Temporary road widening to facilitate sewer works and safe passage of traffic
  • Sanitary sewer works along Nipissing up to 100 Nipissing

Next few weeks (June 2026):

  • Sanitary works on Nipissing ongoing.
  • Storm sewer works along with Road construction works will be commencing along Nipissing
  • To facilitate road and sewer construction, driveway access along Nipissing Road will be temporarily closed up to 3 separate times, for approximately 3 to 5 days each time. Notice’s will be provided to each property confirming date/duration.