Nipissing Road

Project details:

  • Widen the road to three lanes: one in each direction, plus a shared center left-turn lane
  • Build a 3.5-metre-wide multi-use path for walking and cycling (north side)
  • Add a 1.5-metre-wide concrete sidewalk (south side)
  • Replace ditches with curbs and storm sewers, where possible
  • Adjust grading and driveways (some work may be on private property)
  • Upgrade 1,000 metres of sanitary sewer
  • Install a new traffic light at Nipissing Road and Childs Drive

Traffic impacts:

  • Traffic along the entire length of Nipissing will be allowed in the westbound direction only
  • This will remain in place until the Fall of 2026

Work completed to-date (March 26, 2026):

  • Preparation for temporary road widening to facilitate sewer work and safe passage of traffic
  • Sanitary sewer work at intersection of Nipissing and Childs

Next few weeks (*April 6-18):

  • To facilitate sanitary sewer installation across driveways, crews will be operating on a 12-hour shift, consisting of a 7:00 a.m. to 7:00 p.m. day shift and a 7:00 p.m. to 7:00 a.m. night shift.
  • For the night work, the two driveway entrances to the Milton Mall (entrance closest to Dollarama and the delivery entrance behind Shoppers Drug Mart) will only be impacted between 9:00 p.m. and 5:30 a.m.
  • Night work will only proceed once an exemption to the Noise by-law has been received.

*Excluding Saturday to Sunday nights

Share Nipissing Road on Facebook Share Nipissing Road on Twitter Share Nipissing Road on Linkedin Email Nipissing Road link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>