Childs Drive

Project details:

  • Widen the road to add two left-turn lanes onto Ontario Street South
  • Build a 1.5-metre-wide concrete sidewalk (south side, from Ontario Street to Nipissing Road)
  • Upgrade 650 metres of wastewater pipes (from Ontario Street to Satok Crescent)
  • Widen Ontario Street South to add a northbound right-turn lane onto Childs Drive
  • Update the traffic signals at Ontario Street and Childs Drive

Traffic impacts:

  • Childs Drive is now open to two way traffic – please obey onsite traffic control flagging
  • No access to Nipissing Road from Childs Drive (In place until Fall 2026)

Work completed to-date (March 24, 2026):

  • Sanitary Sewer installation completed between Nipissing and Satok (Fall 2025 to early 2026)
  • Temporary restoration work (asphalt) – permanent restoration will occur this summer for private property and 2027 for roadway and sidewalk